Project Status
A Section 36 planning application for Cloud Hill Wind Farm, located close to the existing Whiteside Hill Wind Farm, approximately 4.5 km south of Sanquhar, and 4 km south-east of Kirkconnel, in Dumfries and Galloway has been submitted to the Scottish Government’s Energy Consent Unit.
The application was lodged in August 2023, and the formal notice detailing the submission of the application under the Electricity Act 1989 is available here.
As the development is over 50 MW, the application will be considered by Scottish Ministers. Representations on the application can be made here until 19 November 2023 quoting the application reference ECU00003461.
About the Project
The application is for a wind farm of 11 turbines, each with a maximum tip height of up to 180 m. The turbines will be co-located with a battery energy storage system (BESS). Other infrastructure onsite will include a substation and control room, access tracks, a temporary construction compound, and a permanent met mast of up to 100 m.
Key Facts
- 11 x 6 MW turbines;
- Turbine height 180m ground to tip;
- Capacity over 60 MW;
- Potential to generate electricity for over 59,000 households*;
- Over £10 million in community funds over 35 years of operation;
- The site is located out with any environmental designations or protected landscapes;
- Bespoke Biodiversity Enhancement Plan to improve local ecology and peatlands;
- With a grid connection of 2028, the project will contribute to Scottish Government’s Energy Strategy targets of 20 GW onshore wind.
Site Location
The site location for the wind farm is shown in the map below.
Design Process
An EIA scoping exercise and consultation with community councils and the public took place throughout 2022 and 2023. Since scoping, the number of turbines has been was reduced by three, from 14 to 11. The location of the remaining turbines was shaped through an iterative design process to minimise visibility and environmental impact. This included using the existing onsite access tracks to minimise the footprint of the wind farm.
Feedback from consultations with the public, community councils and organisations such as Nature Scot, Scottish Environment Protection Agency, and Dumfries & Galloway Council have helped shaped the final design.
Key Viewpoints Map
The map below shows before and after images of some key viewpoints associated with the project . A comprehensive library of viewpoints are available in the application documents.
Viewpoint Image Gallery
Additional Resources
- Formal Notice (2023)
- Non-Technical Summary (NTS)
- Application Documents (October 2023)
- Planning Statement
- Pre-Application Consultation Report
- Pre-Application Consultation Report - Appendix 1 - Combined D&G Standard Averts
- Pre-Application Consultation Report - Appendix 2 - Combined Nithsdale Times Adverts
- Pre-Application Consultation Report - Appendix 2 - Combined Nithsdale Times
- Pre-Application Consultation Report - Appendix 3 - Combined KKS News Adverts
- Pre-Application Consultation Report - Appendix 4 - Combined Online Adverts
- Pre-Application Consultation Report - Appendix 5 - Posters Combined
- Pre-Application Consultation Report - Appendix 6 - Leaflet
- Pre-Application Consultation Report - Appendix 7 - Combined Boards - Round 1 Exhibition LR Part 2
- Pre-Application Consultation Report - Appendix 7 - Combined Boards - Round 1 Exhibition LR Part 1
- Pre-Application Consultation Report - Appendix 7 - Combined Boards - Round 1 - Exhibition LR - Part 3
- Pre-Application Consultation Report - Appendix 8 - Combined Boards - Round 2 Exhibition LR Part 1
- Pre-Application Consultation Report - Appendix 8 - Combined Boards - Round 2 Exhibition LR Part 2
- Pre-Application Consultation Report - Appendix 8 - Combined Boards - Round 2 Exhibition LR Part 3
- Pre-Application Consultation Report - Appendix 8 - Combined Boards - Round 2 - Exhibition LR Part 4
- Volume 1 - EIA Report
- Volume 2a - Figures excl. LVIA Cover and Contents
- Volume 2a - Figure 1.1 - Site Location
- Volume 2a - Figure 1.2 - Site Boundary Plan
- Volume 2a - Figure 1.3 - Application Layout
- Volume 2a - Figure 1.3 - Application Layout
- Volume 2a - Figure 3.1 - Constraints Plan
- Volume 2a - Figure 3.2a - Site Design Evolution - Scoping
- Volume 2a - Figure 3.2b - Site Design Evolution - Pre-Chilled
- Volume 2a - Figure 3.2c - Site Design Evolution - Chilled
- Volume 2a - Figure 3.2d - Application Layout
- Volume 2a - Figure 4.1 - Indicative Turbine Elevation
- Volume 2a - Figure 4.2 - Indicative Foundation Design
- Volume 2a - Figure 4.3 - Indicative Crane Hardstanding
- Volume 2a - Figure 4.4 - Indicative Cable Trench Detail
- Volume 2a - Figure 4.5 - Indicative TCC
- Volume 2a - Figure 4.6 - Indicative Substation Compound Layout
- Volume 2a - Figure 4.7 - Indicative Control Building and Elevations
- Volume 2a - Figure 4.8 - Indicative Wind Farm Developers Control Building and Elevations
- Volume 2a - Figure 4.9 - Indicative BESS Design and Elevations
- Volume 2a - Figure 4.10 - Indicative Access Track
- Volume 2a - Figure 4.11 - Indicative Culvert Detail
- Volume 2a - Figure 4.12.1 Indicative Borrow Pit Layout a
- Volume 2a - Figure 4.12.2 - Indicative Borrow Pit Layout b
- Volume 2a - Figure 4.12.3 - Indicative Borrow Pit Layout c
- Volume 2a - Figure 4.13 - Indicative Met Mast Elevations
- Volume 2a - Figure 7.1 - Designated Sites and Ancient Woodlands
- Volume 2a - Figure 7.2 - Carbon Peatland
- Volume 2a - Figure 7.3 - National Vegetation Classifications
- Volume 2a - Figure 7.4 - Potential Groundwater Dependent Terrestrial Ecosystems
- Volume 2a - Figure 7.5 - Protected Species
- Volume 2a - Figure 7.6 - Anabat Locations and Preliminary Bat Roost Assessment Results
- Volume 2a - Figure 7.7 - Bat Common Pipistrelle
- Volume 2a - Figure 7.8 - Bat Soprano Pipistrelle
- Volume 2a - Figure 7.9 - Bat Nyctalus sp.
- Volume 2a - Figure 7.10 - Electrofishing Locations and Survey Results
- Volume 2a - Figure 7.11 - oBEMP
- Volume 2a - Figure 8.1 - Vantage Points and Viewsheds
- Volume 2a - Figure 8.2 - Survey and Study Areas
- Volume 2a - Figure 8.3 - Designated Sites
- Volume 2a - Figure 8.4 - Connectivity Distance Review
- Volume 2a - Figure 8.5 - Black Grouse Lek Locations
- Volume 2a - Figure 8.6 - FA Black Grouse Flight Activity
- Volume 2a - Figure 8.7 - Raptor and Owl Flight Activity
- Volume 2a - Figure 8.8 - Goshawk Flight Activity
- Volume 2a - Figure 8.9 - Hen Harrier Flight Activity
- Volume 2a - Figure 8.10 - FA Merlin
- Volume 2 a - Figure 8.11 - FA Osprey
- Volume 2a - Figure 8.12 - FA Peregrine
- Volume 2a - Figure 8.13 - FA Red Kite
- Volume 2a - Figure 8.14 - Breeding Wader Activity
- Volume 2a - Figure 8.15 - FA Curlew
- Volume 2a - Figure 8.16 - FA Golden Plover
- Volume 2a - Figure 8.17 - FA Pink Footed Goose
- Volume 2a - Figure 9.1 - Site Location and Study Areas
- Volume 2a - Figure 9.2 - Heritage Assets within 1km Study Area
- Volume 2a - Figure 9.3 - Prehistoric Heritage Assets
- Volume 2a - Figure 9.4 - Post-Medieval Heritage Assets
- Volume 2a - Figure 9.5 - Medieval Heritage Assets
- Volume 2a - Figure 9.6 - 1888 OS Map
- Volume 2a - Figure 9.7 - 1937 OS Map
- Volume 2a - Figure 9.8 - Designated Assets within 5km
- Volume 2a - Figure 9.9 Designated Heritage Assets between 5-15km with Cumulatives
- Volume 2a - Figure 9.10 - Designated Heritage Assets between 5-15km North West
- Volume 2a - Figure 9.11 - Designated Heritage Assets between 5-15km North East
- Volume 2a - Figure 9.12 - Designated Heritage Assets between 5-15km South East
- Volume 2a - Figure 9.13 - Designated Heritage Assets between 5-15km South West
- Volume 2a - Figure 10.1 - Bedrock Geology
- Volume 2a - Figure 10.2 - Superficial Soils
- Volume 2a - Figure 10.3 - National Soils Maps of Scotkan
- Volume 2a - Figure 10.4 - Extract from Carbon - Peatland 2016 Map
- Volume 2a - Figure 10.5 - Interpolated Peat Depths
- Volume 2a - Figure 11.1 - Hydrology Study Areas
- Volume 2a - Figure 11.2 - Hydrological Catchments
- Volume 2a - Figure 11.3 - Hydrological Features
- Volume 2a - Figure 11.4 - Watercourse Crossings
- Volume 2a - Figure 11.5 - Groundwater Dependent Terrestrial Ecosystems
- Volume 2a - Figure 12.1 - Cumulative Noise Contour Plot incl. Sanquhar II
- Volume 2a - Figure 12.2 - Cumulative Noise Contour Plot excl. Sanquhar II
- Volume 2a - Figure 12.3 - Noise Contour Plot
- Volume 2a - Figure 13.1 - Abnormal Load Route to Site
- Volume 2a - Figure 13.2 - General Construction Traffic Route to Site
- Volume 2a - Figure 13.3 - Traffic Count Locations
- Volume 2a - Figure 13.4a - RTC Assessment A70 between the A76 and Barr Quarries
- Volume 2a - Figure 13.4b - RTC Assessment A76 - Auckinleck to Sanquhar
- Volume 2a - Figure 13.4c - RTC Assessment A76 - Sanquhar to Barburgh Mill Quarry
- Volume 2a - Figure 13.5 - Indicative Site Access Junction
- Volume 2a - Figure 14.1 - Recreational Routes Map
- Volume 2a - Figure 14.2 - Recreational and Tourist Receptors Map
- Volume 2a - Figure 14.3 - Southern Upland Way within the Site Boundary
- Volume 2a - Figure 16.1 - Shadow Flicker Casting Map
- Volume 2a - Figures excl. LVIA Cover and Contents
- Volume 2b - Figure 6.01 - Study Area
- Volume 2b - Figure 6.02a - Land Character Assessment
- Volume 2b - Figure 6.02b - Land Character Legend
- Volume 2b - Figure 6.03 - Design Wild Landscape Areas
- Volume 2b - Figure 6.04 - Figure 6.04 - Visual Receptors
- Volume 2b - Figure 6.05a - Viewpoints Blade Tip Zone of Theoretical Visibility
- Volume 2b - Figure 6.05b - Viewpoints Blade Tip ZTV 20km
- Volume 2b - Figure 6.06a - Viewpoint Hub Height Zone of Theoretical Visibility
- Volume 2b - Figure 6.06b - Viewpoint Hub Height Zone of Theoretical Visibility 20km
- Volume 2b - Figure 6.07 - Horizontal Angle Blade Tip ZTV and Viewpoints
- Volume 2b - Figure 6.08 - ZTV LCA 20km
- Volume 2b - Figure 6.09a - ZTV Designations
- Volume 2b - Figure 6.09b - ZTV Designations
- Volume 2b - Figure 6.10 - Visual Receptors ZTV
- Volume 2b - Figure 6.11 - Composite Map
- Volume 2b - Figure 6.12 - Cumulative Wind Farms
- Volume 2b - Figure 6.13a - Cumulative ZTV
- Volume 2b - Figure 6.13b - Cumulative ZTV
- Volume 2b - Figure 6.13c - Cumulative ZTV
- Volume 2b - Figure 6.13d - Cumulative ZTV
- Volume 2b - Figure 6.13e - Cumulative ZTV
- Volume 2b - Figure 6.13f - Cumulative ZTV
- Volume 2b - Figure 6.13g - Cumulative ZTV
- Volume 2b - Figure 6.13h - Cumulative ZTV
- Volume 2b - Figure 6.13i - Cumulative ZTV
- Volume 2b - Figure 6.13j - Cumulative ZTV
- Volume 2b - Figure 6.13k - Cumulative ZTV
- Volume 2b - Figure 6.14 - Baseline Light Pollution
- Volume 2b - Figure 6.15 - ZTV Turbine Hub Lighting
- Volume 2b - Figure 6.16 - Lighting Intensity
- Volume 2b - LVIA Figures Cover and Contents
- Volume 2c - Figure 6.17a-i - VP 1 A76 Sanquhar Castle
- Volume 2c - Figure 6.18a-f - VP 2 Sanquhar Church Road
- Volume 2c - Figure 6.19a-i - VP 3 Kirconnel
- Volume 2c - Figure 6.20a-j - VP 4 Euchan Water Minor Road
- Volume 2c - Figure 6.12a-g VP 5 Shiel Scar Water Minor Road
- Volume 2c - Figure 6.22a-e VP 6 Mennock
- Volume 2c - Figure 6.23a-e VP 7 Southern Upland Way East of Sanquhar
- Volume 2c - Figure 6.24a-g - VP 8 Polgown Scaur Water Minor Road
- Volume 2c - Figure 6.25a-d - VP 9 Durisdeer
- Volume 2c - Figure 6.26a-g - VP 10 Wauk Hill
- Volume 2c - Figure 6.27a-g - VP 11 Benbrack
- Volume 2c - Figure 6.28a-g - VP 12 Cairnsmore of Carsphairn
- Volume 2c - Figure 6.29a-g - VP 13 Blackcraig
- Volume 2c - Figure 6.30a-g - VP 14 Corsencon Hill
- Volume 2c - Figure 6.31a-f - VP 15 Todholes Hill
- Volume 2c - Figure 6.32a-e - VP 16 Lowther East Mount
- Volume 2c - Figure 6.33a-d - VP 17 Meikle Millylea
- Volume 2c - Figure 6.34a-e - VP 18 Southern Upland Way Coupland Knowe
- Volume 2c - Figure 6.35a-f - VP 19 Southern Upland Way Glengaber Hill
- Volume 2c - Figure 6.36a-g - VP 20 Cairnkinna
- Volume 2c - Figure 6.37a-e - VP 21 Crawick Multiverse
- Volume 2c - Figure 6.38a-g VP 22 Auchengibbert Hill
- Volume 2c - Figure 6.39a-c - VP 23 Colt Hill
- Volume 2c - Figure 6.40a-b - VP 24 Glenwhargen Scaur Water Minor Road
- Volume 2c - Figure 6.41a-b - VP 25 Auchentaggart
- Volume 2c - Figure 6.42a-c - VP 26 Kelloholm
- Volume 2c - Figure 6.43a-c - VP 27 Whing Head
- Volume 2c - Figure 9.14-9.27 - Heritage Visualisations - Part 1
- Volume 2c - Figure 9.14-9.27 - Heritage Visualisations - Part 2
- Volume 3 - Appendix 2.1 - Gatecheck Report
- Volume 3 - Appendix 6.1 - LVIA Methodology
- Volume 3 - Appendix 6.2 - Residential Visual Amenity Assessment
- Volume 3 - Appendix 6.3 - Visual Assessment of Visible Aviation Lighting
- Volume 3 - Appendix 7.1 - National Vegetation Classification - Habitats Survey
- Volume 3 - Appendix 7.2 - Protected Species Survey Report
- Volume 3 - Appendix 7.3 - Bat Activity Analysis
- Volume 3 - Appendix 7.4 - Electrofishing Survey Report
- Volume 3 - Appendix 7.5 - Outline Species Protection Plan
- Volume 3 - Appendix 7.6 - Outline Biodiversity Enhancement Management Plan
- Volume 3 - Appendix 8.1 - Ornithology
- Volume 3 - Appendix 9.1 - Archaeological Desk-Based Assessment - Part 1
- Volume 3 - Appendix 9.1 - Archaeological Desk-Based Assessment - Part 2
- Volume 3 - Appendix 9.2 - Setting Assessment 5km
- Volume 3 - Appendix 9.3 - Setting Sieving Exercise for Designated Assets between 5 and 15km
- Volume 3 - Appendix 9.4 - Setting Assessment 5-15km
- Volume 3 - Appendix 10.1 - Peat Slide Risk Assessment
- Volume 3 - Appendix 10.2 - Outline Peat Management Plan
- Volume 3 - Appendix 10.3 - Preliminary Borrow Pit Assessment ERM
- Volume 3 - Appendix 11.1 - Private Water Supply Risk Assessment
- Volume 3 - Appendix 11.2 - Outline Water Construction Environmental Management Plan
- Volume 3 - Appendix 12.1 - Cumulative Sound Power Levels
- Volume 3 - Appendix 12.2 - Background Noise Survey Record Sheets
- Volume 3 - Appendix 13.1 - Abnormal Load Route Assessment - Part 1
- Volume 3 - Appendix 13.1 - Abnormal Load Route Assessment - Part 2
- Volume 3 - Appendix 13.1 - Abnormal Load Route Assessment - Part 3
- Volume 3 - Appendix 14.1 - Access Management Plan
- Volume 3 - Appendix 14.2 - Assessment Methodology for Socio-economics, Tourism, Recreation, and Land Use
- Volume 3 - Appendix 15.1 - Carbon Calculations
- Volume 3 - Appendix 16.1 - Aviation Screening Assessment
- Volume 3 - EIA Report Technical Appendices Front Cover and ToC
- Volume 4 - EIA Report Non-Technical Summary
- Pre-Application Consultation Report
- Scoping Report
- Business Leaflet (October 2023)
Community Benefits
BayWa r.e UK is committed to supporting communities that neighbour our wind farm developments. In many cases this support takes the form of an annual community fund which can provide a valuable, long term, sustainable, and reliable source of income for communities.
This flexible funding can be used to address what is important to communities with the potential to fund large and small projects as well as capital, and harder to fund revenue activities. There is also significant potential for this private sector funding to be used to lever additional match funding making it worth even more to the community.
A community benefit package of £5,000 per installed MW will be offered annually for the life of the Cloud Hill Wind Farm. This is estimated to be £308,000 per year index linked, totalling over £10m across the 35-year operation period.
Local Business Register
A range of services are required during the construction and operational phases of a project and the Cloud Hill Wind Farm presents opportunities for local businesses with the right skills and services. If you are interested in working with us, get in touch by emailing CloudHillWindfarm(at)baywa-re.co.uk to be added to our Local Suppliers Database.
Engaging with the Community
The development team at BayWa r.e. has undertaken extensive public consultation throughout the Cloud Hill development phase. Our aim has been to ensure the views of local people have been considered in the design of the wind farm and everyone in the local area is aware of the application.
Public consultation has included exhibitions, and regular meetings with the Community Councils of Royal Burgh of Sanquhar; Kelloholm and Kirkconnel, and Penpont. A dedicated project website provided regular updates throughout the development phase. Newsletters were also distributed to the local community at key stages.
*Calculated using the most recent statistics from DESNZ showing that annual GB average domestic household consumption is 3,509kWh (as of December 2022, updated annually): number of megawatts installed, multiplied by a site specific load factor expressed as a fraction of 1, multiplied by number of hours in a year, divided by average annual domestic electricity consumption expressed in MWh.