Oaklands Farm Solar Park

Location near Rosliston and Walton-on-Trent, South Derbyshire

Project Overview

Oaklands Farm Solar Park is a 151.1 MW renewable energy project being developed by BayWa r.e.. Located near Rosliston and Walton-on-Trent, the project will connect to the existing Drakelow Substation in South Derbyshire.

The project received planning consent in June 2025 and is now in the construction phase.

This page will be updated regularly with information on construction activity, traffic management and key project milestones to help keep the local community informed.

If you would like to receive occasional updates by email, you can contact the project team to join the community mailing list:

info.oaklands-solarfarm@baywa-re.co.uk

You can also reach the community relations team by calling 0800 652 5267

Project Updates

Planned works for week commencing 26 October 2026

Work will continue at the Oaklands site this week. The main activities planned are:

  • Haul Road and Access Works nearing completion

    • Final works ongoing and start of removal of equipment as the work is completed

  • Cable route construction ongoing

  • Traffic Note

    • Residents may notice construction vehicles travelling to and from the site while these works are underway. Vehicles associated with the works will continue to use the agreed construction routes. These works form part of the ongoing preparation of the site ahead of the main construction phase.

Other Updates

Work will continue on the existing access road, with completion of the section connecting to Coton Road expected by the end of Monday. Other activities planned for next week include:

  • Completing the existing access road and installing additional passing places.

  • Continuing work on drainage features, including V-ditches, settlement basins and flush crossings.

  • Completing fencing at junctions.

  • Continuing to operate the temporary four-way traffic lights on Rosliston Road while arrangements for the permanent installation of the haul road traffic lights are confirmed.

Deliveries and traffic management

Stone deliveries are nearing completion. No stone deliveries are expected on Monday, with fewer than six loads per day anticipated for the remainder of the week. Some days may have no deliveries.

PSUK/Lydons will continue working at the Walton Road end of the haul road, with work progressing away from Walton Road and further into the site each day. Sand deliveries are also expected for these works, at approximately four to five loads on some days, but not every day.

The main activity likely to be noticeable to local residents will be the completion of the existing access road connecting to Coton Road, which is expected to finish by the end of Monday.

Oaklands Farm Solar Park is now in the Haul Road and Cable Route construction phase, with some early preparation underway before the main construction of the solar site begins. We currently expect construction of the solar park to start in Q1 2027.

Oaklands Farm Solar Park has submitted a Non-Material Change (NMC) application to make minor tweaks to some design parameters.

Details of the proposed changes, including the NMC application documents, are available to view on the Planning Inspectorate’s project website.

The consultation period for the NMC application has now closed. Thank you to everyone who took the time to review the proposals and submit representations through the Planning Inspectorate’s consultation process.

The NMC application is now being considered by the Secretary of State for Energy Security and Net Zero, supported by the Planning Inspectorate and relevant authorities.

We will continue to provide updates as the process progresses.

If you have questions about the NMC application process, please contact the Planning Inspectorate at OaklandsFarmSolar@planninginspectorate.gov.uk

Construction Timeline

The build phase is anticipated to take approximately 20–24 months, with the solar farm expected to become operational by the end of 2027/early 2028, when it will begin generating renewable electricity.

(Timings are indicative and may change as construction progresses)

Planning consent granted

June 2025 under the Nationally Significant Infrastructure Project regime

Discharge of planning requirements

Ongoing

Site preparation works

Ongoing

Phase 1: Haul Road

August 2026 – October 2026

Phase 2: Cable Route

October 2026 – July 2027

Phase 3: Internal Roads

January 2027 – December 2027 (indicative)

Phase 4: PV Plant

February 2027 – March 2028 (indicative)

Phase 5: Oaklands Substation

November 2026 – November 2027 (indicative)

Phase 6: Drakelow Substation

November 2026 – October 2027 (indicative)

Solar farm operational

Targeted for end of 2027

Managing Construction Activity

During construction, some short-term temporary changes are expected in the local area. These will be carefully managed to minimise disruption wherever possible.

  • Some additional construction vehicles will use approved routes.

  • A new private access road from Walton Road will help reduce traffic impacts on local roads.

  • Delivery times will be planned carefully, and any significant vehicle movements will be communicated in advance where possible. The largest deliveries will be the two high-voltage transformers required to connect the substation to the grid at the appropriate voltage. These are expected to arrive in January – February 2027.

  • Work will follow approved working hours and environmental limits.

  • Higher-noise activities will be scheduled considerately.

  • Dust control measures (such as water suppression and careful material handling) will help keep the site safe and tidy.

  • Work will follow approved environmental plans and planning conditions.

  • Ecological specialists will oversee sensitive areas where needed to safeguard wildlife and habitats.

  • Measures will be in place to protect nearby watercourses and manage drainage responsibly.   

  • Landscaping and habitat management will be ongoing as work progresses.

The construction activity is temporary, and we are committed to minimising impacts while keeping the community informed as the project moves forward.

Full details of the construction activity and transport maps are available on the exhibition boards here.

Traffic Management Group

As part of the project’s continued engagement with the local community, a Traffic Management Group will be set up. Alongside working with the local authorities, this group’s regular meetings will help inform areas of concern, provide an opportunity for updates and ensure disruption is kept to a minimum for the local community.

The group will help:

  • Implement mitigation measures.

  • Ensure contractor obligations are met as set out in the Construction Transport Management Plan (CTMP).

  • Suggest suitable changes to the final CTMP bases on the success of mitigation measures.

National Highways, Staffordshire County Council, Derbyshire County Council and South Derbyshire District Council will be asked to provide representatives to the Traffic Management Group.

More about the Project

In March 2026, we shared our latest community newsletter, followed by a drop‑in event on 22 April 2026, where local residents were able to speak with the team and hear the latest project updates. You can view the newsletter and event materials here.

The development comprises a solar farm plus energy storage facility covering approximately 400 acres at Oaklands Farm.

The expected generating capacity of the project at this stage is 151.1 MW of solar power, and up to 37.5 MW of energy storage capacity.

The project will connect to the grid via an underground cable to Drakelow Substation located to the north of the site.

Community and Local Benefits

Once the solar park is operational, the project will provide £55,000 a year, index‑linked, to support local initiatives.

This funding will be managed independently on behalf of the community, with decisions made by local residents and community representatives. Our role is simply to provide the funding — not to run the scheme.

We are encouraging people living closest to the site to share their ideas on how the fund could be shaped and what kinds of local projects it might support. You can send your suggestions using the contact provided above.

Construction Opportunities

  • As the project progresses through construction, there may be local economic opportunities including opportunities for local contractors and suppliers.

  • If you would like to register your interest and join our supplier database, please contact info.oaklands-solarfarm@baywa-re.co.uk

Aside from community benefits, the project will also include additional hedgerow planting. management and further grassland and wildflower enhancements.

Resources

Exhibition Boards - April 2026
Newsletter - April 2026

Stay Informed

We are committed to keeping the local community updated throughout the construction phase.

Check this page regularly for the latest updates at key milestones.

If you’d like to receive occasional updates by email, you can contact the project team to join the project mailing list.

You can reach the community relations team by calling 0800 652 5267

Contact the Construction Team

Please get in touch if you have any questions or require further information.

Heli Felix Nascimento
Solar Project Manager
+44 1414 680 580
Write an email